Prima pagină » Diverse » Trace, the builder with the most PROGRESS on a highway segment registered in December

Trace, the builder with the most PROGRESS on a highway segment registered in December

Bogdan Pavel

The Trace – Coni association, the builder of segment 2, Mizil – Pietroasele (28 km) of the Ploiești-Buzău Motorway, part of the Moldova Motorway (A7), registered the largest advance of almost 8% in the top of the highway and express road builders list in December. In the last month of 2023, Trace works on the concrete structures that support the 15 bridges on the Mizil-Pietroasele segment. That time, a Gândul team was on site and monitored the work.

Whether we are talking about the longest bridge of the segment built by Trace, the one on a metal deck structure at kilometer 38 + 309, or the one with 40-metre concrete beams at kilometer 45+407, the activity is intense. The workers are working on the iron-concrete mesh, which will reinforce the supporting pillar, and on the formwork to prepare the pouring of concrete.

„For our part we have 15 bridges. Here is the largest of the bridges which stands on metal structure. The distance for metal bridges is longer than for normal concrete bridges,” Trace Romania project manager Georgy Ivanov points out.

No less than 80 piles were drilled to a depth of 25 meters so that the structures supporting the with a metal deck bridge are well fixed in the ground.

„The structure on the metal deck is longer than the concrete beams. The concrete beams are made at a length of 24-40 meters, those on the metal deck are made at 60 meters”, explains the site manager Ștefan Stan.

„The concrete structure does not affect the running surface”

He assures us that the 180-metre-long bridge will have no asphalt problems.

“They have their own slip joint, they have their own stages. So, it has nothing to do with the asphalt, the metal deck structure, the concrete structure, so it doesn’t affect the road surface at all,” says Stan.

And at the largest bridge with concrete beams, a team of workers „braces” the concrete iron reinforcement. And its piles were drilled at 25 meters and the abutments that will support the 40-metre-long concrete beams are impressive. From level 0 to 8 m, where the beams will be installed, 600 cubic meters of concrete have been poured in one abutment alone.

„Now we’ve brought it to the waterproofing stage, which is what comes into contact with the ground, and we’re getting ready for reinforcement, for formwork and for concreting the inverted wall, the guard wall, which is at the top of the slab,” Stefan Stan explains this stage of the work.

„We work with Ferrobeton, this is our producer,” Ivanov said.

The works are conform scheduled

Trace’s Romania project manager said the works are on schedule.

„We don’t have to hurry, we don’t have to go slower, we have to go according to our schedule. Quality and safety, first of all,” concluded Ivanov.

According to Georgy Ivanov, in October 2024 the works will be completed. The Bulgarian company Trace has 25 years of experience in the construction of transport infrastructure, in the Balkans, internationally. It is listed on the Sofia Stock Exchange since 2007. Trace was designated the winner on lot 2 of the Ploiești-Buzău highway, part of the Moldovei Highway, alongside the Romanians from Coni. On June 7, 2022, the contract was signed, and the order to start the works was issued on August 11.

Read also:

EXCLUSIV | Lucrările pe Lotul 2 al Autostrăzii Ploiești – Buzău, construit de Asocierea Coni-Trace, aproape de 50%

EXCLUSIV VIDEO | Trace has started technological tests at the asphalt production plant needed for Lot 2 of the Ploiesti-Buzău Motorway

VIDEO EXCLUSIV | Trace solutions and strategies for large, complex and difficult infrastructure works in Serbia and Bulgaria

Comentarii 0

Lasă un răspuns

Trebuie să fii autentificat pentru a publica un comentariu.
Vă rugăm să țineți cont că folosirea injuriilor, a limbajului instigator la ură, a apelurilor la violență sau trimiterea repetată, în mod abuziv, a aceluiași comentariu pot duce nu doar la ștergerea mesajului, ci și la suspendarea temporară a dreptului de a comenta. Site-ul nostru încurajează dezbaterile aprinse, dar civilizate. Vă mulțumim pentru înțelegere și pentru contribuția la o discuție bazată pe argumente, nu pe atacuri.

Recomandarea video

Mediafax
1.000 de euro intră direct pe card, fără nicio cerere. 11 milioane de familii pot primi banii
Digi24
Pe cine ar vota românii dacă duminică ar avea loc alegeri. Un singur partid a crescut în preferințele de vot în ultima lună
Cancan.ro
Ce au făcut Valentina și Vlad cu o zi înainte de tragedie. 'Până la 12 şi ceva a...
Prosport.ro
FOTO. Diana Munteanu, sesiune foto spectaculoasă într-o fustă transparentă: „Ai defecte?”
Adevarul
Britanicii anunță dezastrul pentru Kiev. Generalul român care a condus o divizie NATO spune ce poate salva Ucraina
Mediafax
TAROM, spre privatizare, Poliția se reorganizează. Marile schimbări pregătite de Mureșan
Click
Mărturisire neașteptată făcută de Cheloo la „Asia Express” despre moartea mamei sale: „A fost decizia ei”
Digi24
Domul de căldură revine peste Europa. Zonele în care se vor înregistra din nou maxime de 40 de grade
Cancan.ro
Cine este tatăl Valentinei, tânăra găsită fără suflare în Olt, și cu ce se ocupă. Este foarte cunoscut în Filiași
Ce se întâmplă doctore
O recunoști pe fetița cu ochii verzi din fotografia aceasta? Astăzi este una dintre cele mai iubite artiste din România
Ciao.ro
Cum au arătat Andreea Esca, Delia sau Andra când s-au căsătorit. Andreea Bănică a strălucit într-o rochie minusculă
Promotor.ro
Am testat noul Volkswagen T-Roc. 150 CP, DSG și un consum surprinzător de apropiat de estimarea WLTP
Descopera.ro
Discursul care a prevestit Primul Război Mondial
Râzi cu lacrimi
BANCUL ZILEI. Ea: – Wow, cină la lumina lumânărilor! De unde ți-a venit ideea?
Descopera.ro
Ce a dezvăluit un dinte vechi de 66 de milioane de ani despre Tyrannosaurus rex?
Mediafax Italia
BOMBĂ | Ce dezvăluie presa din Italia despre Călin Georgescu
Mediafax Spania
A EXPLODAT PREȚUL roșiilor! Care este motivul pe care îl invocă fermierii